It will take five builders 62 days to complete a particular project. At this rate, how long would the project take if there were only two builders?(SHOW WORK)

Respuesta :

Answer:

2 builder complete work = 155 days

Step-by-step explanation:

Given:

5 builder complete work = 62 days

So,

1 builder complete work = 62 days × 5

if,

2 builder complete work = [62 days × 5] / 2

2 builder complete work = 155 days