Seudónimo Seudónimo
  • 13-07-2021
  • Mathematics
contestada

A construction crew is completing about 40 yards of a new highway each day. At this rate, how long will it take them to complete a stretch of 1.6 miles?

Respuesta :

onyikeinnocent
onyikeinnocent onyikeinnocent
  • 24-07-2021

70 days

that is the procedure above

Answer Link

Otras preguntas

PLEASE HELP NEED TO PASS
muslims believe that the prophet ___received the word of ___ from an angel in the mountains around mecca
Read the following excerpt from Kurt Vonnegut's "Harrison Bergeron": "You been so tired lately—kind of wore out," said Hazel. "If there was just some way we co
Why is carbon considered tetravalent?
The smallest angle of rotational symmetry for a regular polygon is 30°. How many sides does the regular polygon have?
PLZZZZZZZZZZ HELPPPPPPPPPPP!!!!!!!!!
Mustafa’s horse ate 6,400 pounds of hay last year. How could Mustafa determine the number of tons of hay his horse ate last year?
The conflict style where one has a low concern for him/herself and a high concern for others is called
What is the simplified form of 4x plus 2 over x plus 5 minus the fraction 3x minus 1 over x plus 5
Does a window air conditioner pull air from outside