It took 6 people to paint several offices in 5 days. how many more people need to be hired to complete the same job in 3 days

Respuesta :

Davidfridman
Davidfridman Davidfridman
  • 12-01-2018
it would be 4 more people
Answer Link
eudora eudora
  • 15-10-2019

Answer:

4 more people

Step-by-step explanation:

6 people can paint several offices in 5 days

1 people can do same work in = 6 × 5 = 30 days

To complete the same job in 3 days people need = [tex]\frac{30}{3}[/tex]

                                                                = 10 people

Need to hire people = 10 - 6 = 4 people

4 more people need to be hired to complete the same job in 3 days.

Answer Link

Otras preguntas

What three things were business people looking for as they explored the world
DATUK168 : SITUS SLOT GACOR REKOMENDASI INFINI88 HANYA DI DATUK168!
I want a detailed explanation please
Complete each row of the table below by filling in the missing prefix or missing exponent.
Which of the following countries was governed by a series of cruel dictators after gaining its independence: A) Kenya B) Uganda C) Samolia D) Democratic Republi
a police car drives with a constant speed of 56 kph .how far can she travel in 3 hours ​
Mga suliranin pangkabuhayan kinaharap ng mga pilipino pagkatapos ng ikalawang digmaan
Ordered by most relevant.
An Advance Directive is a document such as a Living Will and/or Healthcare Surrogate Designation that allows one to give directions about future medical care wh
Question 10 Options: